Fondren Road Reconstruction Project Update
Progress meeting was held on November 17th, 2016 at the project field office. At the meeting the contractor progress was documented and found to be well ahead [...]
Fondren update and Social Service Corridor update attached
November 29, 2016 Phase 2 Contractor has finished work on Dunlap, Clairwood, and Hornwood and is working on completing the rest of Tarnef. Contractor has submitted a [...]
HCAD Property Information Profile
We have been contacted by several Sharpstown Sec. 2 homeowners concerned that "SW Houston Area TIRZ" still appears on their HCAD property information profile. We would like [...]
Fondren Road Construction Update
Beginning Friday, August 5th at 2 am and ending Monday, August 8th at 5 am, Fondren access will be reduced to one lane each direction. Please seek [...]
Fondren Road Reconstruction Project Update
Progress Meeting Contractor has progressed well and is now a head of schedule by 11%. Contractor continues excel and continues to address issues with the local residents [...]
First look inside a private high school’s $20 million expansion
by Cara Smith, Reporter for the Houston Business Journal The campus was built in 1963 for a student body of 400; today St. Agnes has more than [...]
Fondren Road Reconstruction Project Update
Progress Meeting Contractor is has progressed well and is now a head on the scheduled time. Contractor continues to set the bar high and continues to address [...]
TIRZ 20 Update on Sidewalk and Corridor Lighting Installations
Construction has begun on sidewalk and lighting improvements funded by TIRZ 20 to benefit a few areas with high pedestrian traffic. The scope is for sidewalks to [...]
Fondren Road Reconstruction Project Update
Precon Meeting A pre-construction meeting was held for the project on August 24th. The cost of project is, and the length is 600 calendar days. Notice to [...]