Precon Meeting

A pre-construction meeting was held for the project on August 24th. The cost of project is, and the length is 600 calendar days. Notice to proceed was issued for August 31, 2015, making the completion date April 22, 2017.

Progress Meeting

Progress meeting scheduled for September 29, 2015. No information is available at this time.
fondren01

Progress of Work

The Contractor has starting working on the south side of the project, and is removing the medians and interior lanes to start installing storm sewer. Traffic control has been set up starting south of the US 59 intersection.
fondren02

Future Work

The Contractor will continue to focus on installing the storm sewer.
fondren03