CURRENT PROJECTS

2019-12-11T19:45:36-06:00

Harwin and Gessner Intersection Reconstruction

The Southwest Houston Redevelopment Authority (SWHRA) TIRZ 20 authorized Cobb, Fendley & Associates to proceed with preliminary design services for the reconstruction of Harwin Drive and Gessner Road signalized intersection and approaches on August 16, 2018. The major objective for this report is to review and evaluate existing right-of-way, visibility triangles, added capacity, traffic signals, [...]

2016-12-11T23:18:16-06:00

Oak Park Road Construction

During the month of January 2016 CobbFendley has performed the following: At the request of Datavox owners, Mahmoud Salehi, Richard Rodriguez, and Ben Morse met with Datavox owners on January 7, 2016. CobbFendley provided Datavox owners with a project update. Datavox initial concerns were addressed from initial meeting at the project design kick-off back [...]