Progress meeting was held on November 17th, 2016 at the project field office. At the meeting the contractor progress was documented and found to be well ahead of schedule (approximately 26 %). A summary of the contractor’s time and expenditure is as follows: the contractor is roughly 99.6 % complete ($19,999,826.27), with 75% (447 days) of the time expired. Contractor has submitted Pay Estimate #15 for $790,820.88 and CobbFendley has reviewed the pay estimate and concurs with this amount.
Progress of Work
Some highlight of last month’s work are bulleted below
- Contractor is sustainably complete and an inspection is pending.
Future Work
Contractor will be completing clean up and finishing items.
RFIs, Work Change Directives and Change Orders
Change Order 1 for Harwin is executed and has been added to the schedule of values, with an extension of 90 days and a cost of $522,956.40.
Change Order 2 for curb retaining wall is executed and has been added to the schedule of values, at a cost of $265,049.15.